Load Tests

Have you been rated?

OSHA (1910.179(k)(2)) requirements mandate that a unit must be load tested when it is a new installation or has had structural changes from the original rated design. A load test certificate is required to be on file for each unit.

  • Units are load tested at 125% of their capacity unless other wise specified by the manufacturer.
  • We have weights available at our facility for testing.
  • Once completed you will receive a Load Test Certificate

A load test certificate must be kept on file at the facility where the crane is housed. For your safety never overload a crane.